Machine A can do a printing job in 2 hours. Machine B can do the same job in 3 hours. If both machines are used at the same time, how long would it take to complete half the printing job?
Solution
Since Machine A takes 2 hours and Machine B takes 3 hours, Machine A will be able to get more work done than Machine B, if both are used at the same time, in the ratio of 3:2 as shown below.
(Machine A)
Whole job ----- 2 hours
3/5 of job ----- 3/5 x 2 hours = 6/5 hours
Time taken if both machines are used at the same time is 6/5 hours because while Machine A completes 3/5 of the job, Machine B completes the remaining 2/5 of the job.
Time taken for whole job done if both machines are used at same time is therefore 6/5 hours
Time taken for half the job done if both machines are used at the same time is
1/2 x 6/5 hours = 3/5 hour.
Answer: 3/5 hour
This blog is managed by Song Hock Chye, author of Improve Your Thinking Skills in Maths (P1-P3 series), which is published and distributed by EPH.
Thursday, September 24, 2009
Rosyth Sch 2007 PSLE Math Prelim Q40
Labels:
Mathematics,
Rate
Subscribe to:
Post Comments (Atom)
No comments:
Post a Comment