ACS Primary 2009 PSLE Math Prelim Paper 2 Q5

If it takes 1 worker 4 days to paint a flat, how many days will it take 8 workers to paint 4 flats if they all work at the same rate?

Solution

1 worker --> 1 flat, 4 days

8 workers --> 8 flats, 4 days
(8 workers give an output 8 times more)

8 workers --> 4 flats, 2 days
(Same 8 workers need only half the time for 4 flats)

Answer: 2 days